Projects

Wells Fargo Center Neutral Host Cellular DAS System

Wells Fargo Center Neutral Host Cellular DAS System

Philadelphia, Pennsylvania
United States
wells fargo center

Introba provided professional engineering design services for a state-of-the-art neutral host Commercial Cellular DAS throughout all seven levels of the arena including multiband spherical antennas suspended from the Catwalk.

The Wells Fargo Center, one of the busiest arenas in the world, is home to the Philadelphia Flyers of the National Hockey League, the Philadelphia 76ers of the National Basketball Association, and the Philadelphia Wings of the National Lacrosse League.

Project Phases

  • Phase 1: Construction Document Package (Signed/Stamped Design Drawings and Specifications)

  • Phase 2: Construction Administration

Phase 1 Design Tasks: Construction Document Package

  • Validated iBwave RF design based on existing conditions

  • Developed an integrated coaxial cable distribution system supporting the DAS throughout the venue

  • Identified physical infrastructure including telecommunications rooms, conduits, raceways, and other pathway systems

  • Developed equipment room/part plan layouts

  • Developed Rack Elevations and equipment elevation/section views

  • Developed Block/Riser diagrams

  • Developed device mounting details

  • Developed Fiber termination/splice details

  • Developed electrical, mechanical, structural, and telecommunication design and distribution of telecom rooms for active DAS equipment

  • Developed equipment, antenna, and cable schedules

  • Coordinated and Developed RCPs with base building 

  • Developed electrical and telecom drawings for the fit out of a 400 sq ft DAS Point-of-Interface Head-End Room

  • Developed Specifications documents

Phase 2 Project Tasks: Construction Administration

  • Review/Approval of Contractor Submittals, RFI’s and Shop Drawings

  • Monitored construction progress

  • Attendance of construction meetings

  • Developed As-built documentation package

Project Highlights

  • 400+ sq ft Head-End Point-of-Interface Room

  • 258 DAS Remotes and 348 DAS Antennas